PROJECT TITLE:
Elevator Modifications at Several Locations for Monroe Public Schools
PROJECT #:
25103-25104
BRIEF PROJECT DESCRIPTION:
This project consists of work related to the Modernization of the existing elevators at Monroe Highs School and Monroe Middle School, which includes but is not limited to the modifications to the existing elevator equipment rooms, new LED lighting, sump pump installation in the elevator pit with oil separator, and existing fire alarm / sprinkler systems.
SCHEDULE:
Out for Bids |
April 3, 2025 |
Pre-bid Meeting |
Monroe High School, April 17, 2025 @ 3:00pm Monroe Middle School, April 17, 2025 @ 4:00pm |
Official Bidders List |
April 21, 2025 |
Bids Due |
May 1, 2025 @ 3:00pm |
Post Bid Interviews |
May 2-6, 2025 |
Architect Recommendation |
May 7, 2025 |
Owner Awards Project |
May 13, 2025 |
Notice to Proceed Letters |
May 14, 2025 |
Pre-Construction Meeting |
TBD |
Physical Construction |
June 16, 2025 – August 15, 2025 |
Substantial Completion |
August 15, 2025 |
Final Completion |
September 15, 2025 |